What is going on

Solvent-weld joints must be cleaned, primed and cemented in the order given. The gasket seals the jacket at the condensate outlet.

Check in this order

  1. Remove the PVC fittings and gasket from the accessories bag.
  2. Deburr and chamfer both ends of the 1/2 in x 1-1/4 in PVC nipple.
  3. Clean all nipple ends and fittings, then dry them.
  4. For each joint, prime both surfaces, apply cement while the primer is damp, and apply a second coat of cement.
  5. Insert the pipe fully into the fitting with a 1/4 turn while the cement is wet. Wipe off excess and check for a smooth bead all round.
  6. Assemble the 1/2 in nipple to the PVC reducing elbow and let it dry fully.
  7. Slide the gasket over the nipple, push the nipple through the jacket condensate hole, and cement the 1/2 in tee to the nipple with both upright.
  8. Press the reducing elbow and tee together while the cement sets so the gasket compresses.

Applies to: All Ultra models, condensate line at jacket

More boiler guides

Take it to the job

All guides, error codes and tips work offline in the HVACopedia app.

Open the app

Source: Weil-McLain Ultra Series 4 boiler manual, p. 27. Written in our own words; check the manual for your exact model.

For licensed technicians. Gas, electrical and refrigerant work must be done by a qualified, licensed person. Shut off power and gas before servicing, never bypass a safety control, and follow the manufacturer’s manual for the exact model; it and local codes always take priority. HVACopedia is not affiliated with any manufacturer; brand and model names only identify the equipment.