Field wiring steps for the base indoor unit. Wiring in this section is for the base unit only.
Check in this order
- Turn off the main disconnect and lock it out before starting.
- Strip about 1/2 in (12 mm) from signal cable ends and strip the individual wire ends.
- Crimp fork terminals on each wire end.
- Open the front panel and remove the electric control box cover.
- Run the power and signal cables through the wire outlet.
- Match wire colors or labels to the terminal block and screw each fork terminal firmly.
- Clamp the cable so it is not loose and does not strain the fork terminals.
- Reattach the electric box cover.
- Use copper wire only and size wires per NEC and local codes.
- Keep interconnection cable away from copper tube and refrigerant parts.
Applies to: D5FUHA indoor unit
More air handler guides
Take it to the job
All guides, error codes and tips work offline in the HVACopedia app.
Source: D5FUHA service manual, p. 13. Written in our own words; check the manual for your exact model.
For licensed technicians. Gas, electrical and refrigerant work must be done by a qualified, licensed person. Shut off power and gas before servicing, never bypass a safety control, and follow the manufacturer’s manual for the exact model; it and local codes always take priority. HVACopedia is not affiliated with any manufacturer; brand and model names only identify the equipment.