What is going on
Horizontal coils can sit on a platform, truss, hangers or blocks. The coil cabinet must be level side to side and front to back.
Check in this order
- Level the coil cabinet side to side and front to back. Up to 1/2 in of extra slope over the length and depth is allowed toward the drain pan connection.
- Right flow attach field attachment plates to the coil casing with self-tapping screws, then connect the furnace snugly and fasten it.
- Left flow bend the 4 tabs on the right side of the casing, connect the furnace snugly and fasten it with self-tapping screws.
- For either side, seal the joint airtight with an approved material.
- If the coil is wider than the furnace, use a 4 in minimum transition.
Applies to: D5FULA horizontal installs
More air handler guides
Take it to the job
All guides, error codes and tips work offline in the HVACopedia app.
Source: Carrier D5FULA installation instructions, p. 22. Written in our own words; check the manual for your exact model.
For licensed technicians. Gas, electrical and refrigerant work must be done by a qualified, licensed person. Shut off power and gas before servicing, never bypass a safety control, and follow the manufacturer’s manual for the exact model; it and local codes always take priority. HVACopedia is not affiliated with any manufacturer; brand and model names only identify the equipment.