Carrier · Air handler troubleshooting
Flare refrigerant pipe ends
What is going on
A correct flare is needed for an air-tight seal. Once flared, the nut cannot be fitted or turned around.
Check in this order
- Seal the pipe ends with PVC tape after deburring to keep debris out.
- Sheath the pipe with insulation.
- Put the flare nuts on both ends first and check they face the correct direction.
- Remove the PVC tape only when you are ready to flare.
- Clamp the flare block on the pipe end so the pipe extends past the flare form.
- Place the flaring tool on the form and turn the handle clockwise until the pipe is fully flared to the Table 14 dimensions.
- Remove the flaring tool and block, then check the flare for cracks and an even flare.
Applies to: D5FSAA / D5FLAA air handler, copper line set
More air handler guides
Take it to the job
All guides, error codes and tips work offline in the HVACopedia app.
Source: Carrier D5FSAA/D5FLAA installation manual, p. 24. Written in our own words; check the manual for your exact model.
For licensed technicians. Gas, electrical and refrigerant work must be done by a qualified, licensed person. Shut off power and gas before servicing, never bypass a safety control, and follow the manufacturer’s manual for the exact model; it and local codes always take priority. HVACopedia is not affiliated with any manufacturer; brand and model names only identify the equipment.