Carrier · Air handler troubleshooting
Field piping pressure test and evacuation
What is going on
Required checks on field-installed split system piping before refrigerant is charged.
Check in this order
- Pressure test the field piping with an inert gas. Test the low side at its design pressure and the high side at its design pressure, or test the whole system at low side pressure if the sides cannot be isolated.
- Hold the test pressure for at least 1 hour after removing the pressure source. The gauge must show no drop. Gauge resolution must not exceed 5% of test pressure.
- Evacuate the system to the vacuum level specified in the manual or lower. The target is the lesser of 500 microns or the value required by local codes.
- Isolate the system from the vacuum pump. Pressure must not rise above 1500 microns within 10 minutes.
- Leak test field-made indoor refrigerant joints at a minimum of 125% of maximum allowable pressure. Sensitivity must be 1/8 oz (5 g) per year or better. No leak is allowed.
Applies to: Field piping on D5FUHAQ split systems
More air handler guides
Take it to the job
All guides, error codes and tips work offline in the HVACopedia app.
Source: D5FUHAQ Owner's Manual, p. 4. Written in our own words; check the manual for your exact model.
For licensed technicians. Gas, electrical and refrigerant work must be done by a qualified, licensed person. Shut off power and gas before servicing, never bypass a safety control, and follow the manufacturer’s manual for the exact model; it and local codes always take priority. HVACopedia is not affiliated with any manufacturer; brand and model names only identify the equipment.