Connect refrigerant lines to outdoor and indoor units
What is going on
Order of connection and torque method for flare nut joints, plus the nitrogen pressure test for brazed work.
Check in this order
- Connect the outdoor unit end first, then the indoor unit end.
- Connect the low-pressure line before the high-pressure line.
- Put a thin coat of refrigeration oil on the flared ends.
- Line up the centers of the two pipes, then tighten the flare nut by hand as far as possible.
- Hold the unit fitting with a backup wrench and tighten the flare nut with a torque wrench to the value in the flare nut table.
- When brazing, flow nitrogen through the lines and braze the tubing and fittings for a proper seal.
- Pressure test with nitrogen to no more than 500 psig for at least 60 minutes.
- Insulate the suction line completely, including the outdoor unit valves.
- Bundle the power cable, signal cable and piping with binding tape. Keep the signal cable separate from all other wiring.
Applies to: D5FUAA 18K to 60K, field refrigerant piping
More air handler guides
Take it to the job
All guides, error codes and tips work offline in the HVACopedia app.
Source: D5FUAA installation instructions, p. 40. Written in our own words; check the manual for your exact model.
For licensed technicians. Gas, electrical and refrigerant work must be done by a qualified, licensed person. Shut off power and gas before servicing, never bypass a safety control, and follow the manufacturer’s manual for the exact model; it and local codes always take priority. HVACopedia is not affiliated with any manufacturer; brand and model names only identify the equipment.