What is going on

Mounting the control box and cutting the wire opening on the coil interface.

Check in this order

  1. Choose the install location, giving priority to the front of the coil; side or nearby wall is acceptable.
  2. Use a flat-head screwdriver at the marked positions to open the control box cover.
  3. Fold the flange up 90 degrees with bending pliers, then fold the flanges around the opening.
  4. Seal all flange sides with tape and insulate with sponge.
  5. Attach the control box with 3 screws into the pre-drilled holes (right or left side).
  6. Use only the supplied screws or equivalent; maximum screw length is 5/8 in (16 mm) to avoid coil damage (see Table 6).
  7. Cut the cover port only as needed for the wires: a single cut for one wire, or cut along the maximum outline for multiple wires.
  8. Close the control box cover.

Applies to: D5FULA

More air handler guides

Take it to the job

All guides, error codes and tips work offline in the HVACopedia app.

Open the app

Source: D5FULA installation instructions, p. 25-26. Written in our own words; check the manual for your exact model.

For licensed technicians. Gas, electrical and refrigerant work must be done by a qualified, licensed person. Shut off power and gas before servicing, never bypass a safety control, and follow the manufacturer’s manual for the exact model; it and local codes always take priority. HVACopedia is not affiliated with any manufacturer; brand and model names only identify the equipment.