Decommissioning and refrigerant recovery
What is going on
Safe recovery steps before decommissioning a flammable refrigerant system.
Check in this order
- Confirm the technician knows the equipment fully.
- Take an oil and refrigerant sample if analysis may be needed before reuse.
- Make sure electrical power is available, then isolate the system electrically.
- Pump the system down if possible; otherwise make a manifold to recover from several points.
- Place the recovery cylinder on scales before recovery.
- Keep the recovery process supervised at all times.
- Do not fill cylinders above 80% liquid volume.
- Do not exceed the cylinder maximum working pressure.
- Remove filled cylinders and equipment from site promptly and close isolation valves.
- Do not charge recovered refrigerant into another system unless cleaned and checked.
- Label the equipment as decommissioned and emptied, with date and signature.
- Label the equipment as containing flammable refrigerant.
Applies to: Decommissioning flammable refrigerant equipment
More air conditioner guides
Take it to the job
All guides, error codes and tips work offline in the HVACopedia app.
Source: Carrier D5FUHA installation instructions, p. 8. Written in our own words; check the manual for your exact model.
For licensed technicians. Gas, electrical and refrigerant work must be done by a qualified, licensed person. Shut off power and gas before servicing, never bypass a safety control, and follow the manufacturer’s manual for the exact model; it and local codes always take priority. HVACopedia is not affiliated with any manufacturer; brand and model names only identify the equipment.