Carrier · Air conditioner troubleshooting

Decommissioning and refrigerant recovery

D5FUHA

What is going on

Safe recovery steps before decommissioning a flammable refrigerant system.

Check in this order

  1. Confirm the technician knows the equipment fully.
  2. Take an oil and refrigerant sample if analysis may be needed before reuse.
  3. Make sure electrical power is available, then isolate the system electrically.
  4. Pump the system down if possible; otherwise make a manifold to recover from several points.
  5. Place the recovery cylinder on scales before recovery.
  6. Keep the recovery process supervised at all times.
  7. Do not fill cylinders above 80% liquid volume.
  8. Do not exceed the cylinder maximum working pressure.
  9. Remove filled cylinders and equipment from site promptly and close isolation valves.
  10. Do not charge recovered refrigerant into another system unless cleaned and checked.
  11. Label the equipment as decommissioned and emptied, with date and signature.
  12. Label the equipment as containing flammable refrigerant.

Applies to: Decommissioning flammable refrigerant equipment

More air conditioner guides

Take it to the job

All guides, error codes and tips work offline in the HVACopedia app.

Open the app

Source: Carrier D5FUHA installation instructions, p. 8. Written in our own words; check the manual for your exact model.

For licensed technicians. Gas, electrical and refrigerant work must be done by a qualified, licensed person. Shut off power and gas before servicing, never bypass a safety control, and follow the manufacturer’s manual for the exact model; it and local codes always take priority. HVACopedia is not affiliated with any manufacturer; brand and model names only identify the equipment.