FlowMax · Boiler · Standby/shutdown

Switched OFF at the control panel

FLOWMAX 90/120

What happens, in order

  1. Display shows OFF
  2. Heating and DHW frost protection stay active
  3. If the unit was running, post-ventilation, pump overrun and 3-way valve anti-seize function still complete
  4. Remote control, if fitted, stays lit and active
  5. For a long shutdown either cut gas and power and drain heating system and condensate trap, or leave on standby so frost protection keeps working

Applies to: FLOWMAX-90, FLOWMAX-120

Models

FLOWMAX-90FLOWMAX-120

More FlowMax boiler sequences

Take it to the job

Sequences of operation, error codes and tips work offline in the HVACopedia app.

Open the app

Source: FLOWMAX-120 installation manual (DIGITECH PCB SM20021, parameters 4-8, function codes 07/08/28); FLOWMAX-90 user manual (control panel, start-up, diagnostics). Written in our own words; timings can differ by model and software version, so check the manual for your exact unit.

For licensed technicians. Gas, electrical and refrigerant work must be done by a qualified, licensed person. Shut off power and gas before servicing, never bypass a safety control, and follow the manufacturer’s manual for the exact model; it and local codes always take priority. HVACopedia is not affiliated with any manufacturer; brand and model names only identify the equipment.