FlowMax · Boiler · Other

Flue test and legionella functions

FLOWMAX 90/120

What happens, in order

  1. Hold the service button 7 seconds to start the flue test (code 07)
  2. Unit runs at maximum heating output with no modulation for 15 minutes for combustion testing
  3. Pressing the OFF button cancels the flue test
  4. Storage cylinder systems only every 7 days the control heats the cylinder to 60 C regardless of the DHW setpoint (legionella prevention, code 28)

Timings and thresholds

ItemValue
Flue test duration15 min
Legionella interval7 days
Legionella temperature60 C

Applies to: FLOWMAX-120

Models

FLOWMAX-120

More FlowMax boiler sequences

Take it to the job

Sequences of operation, error codes and tips work offline in the HVACopedia app.

Open the app

Source: FLOWMAX-120 installation manual (DIGITECH PCB SM20021, parameters 4-8, function codes 07/08/28). Written in our own words; timings can differ by model and software version, so check the manual for your exact unit.

For licensed technicians. Gas, electrical and refrigerant work must be done by a qualified, licensed person. Shut off power and gas before servicing, never bypass a safety control, and follow the manufacturer’s manual for the exact model; it and local codes always take priority. HVACopedia is not affiliated with any manufacturer; brand and model names only identify the equipment.