What is going on

Figure 15 shows the Easy-Up or field-fabricated manifold layout. Items supplied with the boiler or heat pump are marked in the legend. Everything else is supplied by the installer. Keep tee and header spacing within 8 pipe diameters as shown on the figure. Legend numbers 18, 19, 21, 22, 28 and 29 are not printed, so the parts list below covers only the items that are labelled.

Check in this order

  1. Keep spacing between the marked connections within 8 pipe diameters.
  2. Field pipe the relief valve and its discharge to a drain.
  3. Install the Y-strainer with an 80 mesh screen.
  4. Install isolation valves, purge/drain valves and unions for service access.
  5. Install heat traps where shown.
  6. Confirm the boiler and heat pump supplied drain valves and pressure/temperature gauges are field piped.

Applies to: System Type A, Application A1 piping

More heat pump guides

Take it to the job

All guides, error codes and tips work offline in the HVACopedia app.

Open the app

Source: ECO HP Heat Pump – Application Guide, p. 17. Written in our own words; check the manual for your exact model.

For licensed technicians. Gas, electrical and refrigerant work must be done by a qualified, licensed person. Shut off power and gas before servicing, never bypass a safety control, and follow the manufacturer’s manual for the exact model; it and local codes always take priority. HVACopedia is not affiliated with any manufacturer; brand and model names only identify the equipment.