Weil-McLain · Heat pump troubleshooting

Application B2 piping layout

ECO HP

What is going on

Primary/secondary piping for two space heating zones and a DHW zone, with a boiler circulator and heat pump circulator in the manifold.

Check in this order

  1. Set up the easy-up or field-fabricated manifold for the heat pump and boiler.
  2. Install the boiler circulator (shipped loose with the boiler) on the boiler piping.
  3. Install the heat pump circulator (in the heat pump manifold) with its internal flow check valve.
  4. Install relief valves on the boiler and heat pump and pipe them to drain.
  5. Install isolation valves, Y-strainer with 80 mesh screen, expansion tank, air separator and purge/drain valves.
  6. Install zone valves and zone circulators, and the DHW circulator with DHW temperature and pressure relief valve.
  7. Keep piping within the spacing shown (do not exceed 8 pipe diameters apart).
  8. Install unions where needed for service and add a make-up water supply.

Applies to: System Type B, Application B2

More heat pump guides

Take it to the job

All guides, error codes and tips work offline in the HVACopedia app.

Open the app

Source: ECO HP Heat Pump Application Guide, p. 31. Written in our own words; check the manual for your exact model.

For licensed technicians. Gas, electrical and refrigerant work must be done by a qualified, licensed person. Shut off power and gas before servicing, never bypass a safety control, and follow the manufacturer’s manual for the exact model; it and local codes always take priority. HVACopedia is not affiliated with any manufacturer; brand and model names only identify the equipment.