What is going on

Figure 28 shows the C1 heat pump wiring with a 120 Vac input, the TIU priority end switch for heating, and the indoor unit pump. Figure 29 shows the TIU and its zone circulators. Many diagram labels are garbled, so only the legible points are listed.

Check in this order

  1. Connect the 120 Vac input (L, N, PE) as shown in Figure 28.
  2. Wire the TIU priority end switch (heating) to the heat pump input.
  3. Wire the TIU (SR-503-5) zone circulators per Figure 29.
  4. Confirm the Priority On dipswitch is OFF before commissioning.

Applies to: Application C1, Multi-zone space heating, System Type C

More heat pump guides

Take it to the job

All guides, error codes and tips work offline in the HVACopedia app.

Open the app

Source: ECO HP Heat Pump - Application Guide, p. 46-47. Written in our own words; check the manual for your exact model.

For licensed technicians. Gas, electrical and refrigerant work must be done by a qualified, licensed person. Shut off power and gas before servicing, never bypass a safety control, and follow the manufacturer’s manual for the exact model; it and local codes always take priority. HVACopedia is not affiliated with any manufacturer; brand and model names only identify the equipment.