Heat pump and boiler piping order

ECO HP

What is going on

Heat pump upstream of boiler: the heat pump sees system return temperature while the boiler runs, so both can run together. This layout is normally used with a condensing boiler. Heat pump downstream of boiler: the heat pump sees high return temperatures when the boiler runs and will likely shut down, so concurrent operation is prevented. This layout is normally used with a non-condensing boiler. The boiler connection may be direct or primary/secondary, depending on design intent.

Check in this order

  1. For a condensing boiler where concurrent operation is wanted, pipe the heat pump upstream of the boiler.
  2. For a non-condensing boiler, pipe the heat pump downstream of the boiler.
  3. Confirm whether the boiler connects direct or primary/secondary to the system piping, as the design intends.

Applies to: Heat pump and boiler hydronic piping

More heat pump guides

Take it to the job

All guides, error codes and tips work offline in the HVACopedia app.

Open the app

Source: ECO HP Heat Pump – Application Guide, p. 9. Written in our own words; check the manual for your exact model.

For licensed technicians. Gas, electrical and refrigerant work must be done by a qualified, licensed person. Shut off power and gas before servicing, never bypass a safety control, and follow the manufacturer’s manual for the exact model; it and local codes always take priority. HVACopedia is not affiliated with any manufacturer; brand and model names only identify the equipment.