Viessmann · Boiler troubleshooting
Wire pumps drawing more than 2FLA
What is going on
Pumps above the direct output rating must be switched through a contactor.
Check in this order
- Install a field-supplied contactor or relay rated 120VAC 1A on the DIN rail in the junction box.
- Connect the contactor to the 120V output and power the pump from the field power supply with disconnect and protection.
- Connect the pump to the contactor output.
Applies to: 120V pumps with amperage draw above 2FLA
More boiler guides
Take it to the job
All guides, error codes and tips work offline in the HVACopedia app.
Source: Vitotronic 300 GW6B installation and service manual, p. 32. Written in our own words; check the manual for your exact model.
For licensed technicians. Gas, electrical and refrigerant work must be done by a qualified, licensed person. Shut off power and gas before servicing, never bypass a safety control, and follow the manufacturer’s manual for the exact model; it and local codes always take priority. HVACopedia is not affiliated with any manufacturer; brand and model names only identify the equipment.