Water distribution pipe and drain assembly
What is going on
Build the water distribution pipe from the rod sections, fit the supply nipple and fill/drain valve, and set the R 2 in. plugs so they do not stick out too far.
Check in this order
- Join the rod end and the extension rod with the supplied sheet metal screws. The number and length of rods depend on boiler size.
- Fit a gasket on the flange rod and secure it with the supplied brass screws.
- Slide the water distribution pipe through the lower nipple ports.
- Install the supply nipple in the R c in. opening on the rear cast iron section and fit the supplied fill and drain valve.
- Make sure the distribution pipe openings face upward.
- Apply hemp and pipe dope to the R 2 in. plugs and insert them into the openings in the front section.
- Tighten the plugs with a 1 in. square tube or 1 in. ratchet. The plugs must not protrude more than 9/32 in. (7 mm).
Applies to: Vitorond 200 VD2 320 to 1080
More boiler guides
Take it to the job
All guides, error codes and tips work offline in the HVACopedia app.
Source: Vitorond 200, VD2 Series 320 to 1080 Installation Instructions, p. 17. Written in our own words; check the manual for your exact model.
For licensed technicians. Gas, electrical and refrigerant work must be done by a qualified, licensed person. Shut off power and gas before servicing, never bypass a safety control, and follow the manufacturer’s manual for the exact model; it and local codes always take priority. HVACopedia is not affiliated with any manufacturer; brand and model names only identify the equipment.