Water distribution pipe and drain assembly

Vitorond 200 VD2

What is going on

Build the water distribution pipe from the rod sections, fit the supply nipple and fill/drain valve, and set the R 2 in. plugs so they do not stick out too far.

Check in this order

  1. Join the rod end and the extension rod with the supplied sheet metal screws. The number and length of rods depend on boiler size.
  2. Fit a gasket on the flange rod and secure it with the supplied brass screws.
  3. Slide the water distribution pipe through the lower nipple ports.
  4. Install the supply nipple in the R c in. opening on the rear cast iron section and fit the supplied fill and drain valve.
  5. Make sure the distribution pipe openings face upward.
  6. Apply hemp and pipe dope to the R 2 in. plugs and insert them into the openings in the front section.
  7. Tighten the plugs with a 1 in. square tube or 1 in. ratchet. The plugs must not protrude more than 9/32 in. (7 mm).

Applies to: Vitorond 200 VD2 320 to 1080

More boiler guides

Take it to the job

All guides, error codes and tips work offline in the HVACopedia app.

Open the app

Source: Vitorond 200, VD2 Series 320 to 1080 Installation Instructions, p. 17. Written in our own words; check the manual for your exact model.

For licensed technicians. Gas, electrical and refrigerant work must be done by a qualified, licensed person. Shut off power and gas before servicing, never bypass a safety control, and follow the manufacturer’s manual for the exact model; it and local codes always take priority. HVACopedia is not affiliated with any manufacturer; brand and model names only identify the equipment.