Wall mounting bracket on concrete, wood and metal studs
What is going on
The boiler mounts on a wall bracket. The supplied screws and rawl plugs are only for concrete. Other materials need bolts and anchors rated for 196 lb (86 kg). A loose bracket is a severe safety hazard, so it must be tight and level.
Likely causes
- Bracket not fully secured
- Wall material not suitable for the supplied fixings
Check in this order
- Check the wall condition and confirm it can carry 196 lb (86 kg).
- Concrete mark the holes, drill 10 mm holes, insert the rawl plugs, and fasten the bracket with the supplied screws.
- Wood studs drill 3/16 in. pilot holes at the center of each stud and fasten with bolts.
- Metal studs drill pilot holes at the center of each stud, use the supplied fasteners, and make sure the bracket is level.
- Check the bracket is tight and secure before hanging the boiler.
Applies to: Vitodens 100-W B1HE and B1KE wall-mounted
More boiler guides
Take it to the job
All guides, error codes and tips work offline in the HVACopedia app.
Source: Vitodens 100-W B1HE/B1KE installation manual, p. 13-14. Written in our own words; check the manual for your exact model.
For licensed technicians. Gas, electrical and refrigerant work must be done by a qualified, licensed person. Shut off power and gas before servicing, never bypass a safety control, and follow the manufacturer’s manual for the exact model; it and local codes always take priority. HVACopedia is not affiliated with any manufacturer; brand and model names only identify the equipment.