Moves the top panel screw so the panel can be removed without problems later.
Check in this order
- Move the top panel screw about 3 in. to the left or right of its original position.
- Pre-drill the panel at the new location with the specified pilot drill bit.
- When reinstalling, drill a new pilot hole through the top back panel and into the back panel.
- Reinstall the screw in the new mounting hole.
Applies to: Hydrostat 3250-Plus and Vitotronic installs
More boiler guides
Take it to the job
All guides, error codes and tips work offline in the HVACopedia app.
Source: Vitorond 100 VR1 installation and service manual, pp. 18, 21. Written in our own words; check the manual for your exact model.
For licensed technicians. Gas, electrical and refrigerant work must be done by a qualified, licensed person. Shut off power and gas before servicing, never bypass a safety control, and follow the manufacturer’s manual for the exact model; it and local codes always take priority. HVACopedia is not affiliated with any manufacturer; brand and model names only identify the equipment.