Pressure relief valve installation

Vitorond 100

What is going on

Install the factory-supplied approved pressure relief valve on the boiler water supply connection. Do not put an isolation valve between the boiler and the relief valve. Pipe the discharge close to a floor drain, never outdoors.

Check in this order

  1. Install the pressure relief valve on the boiler water supply connection.
  2. Install the discharge pipe, minimum 3/4 in, unthreaded at the end.
  3. End the discharge pipe about 6 in (150 mm) above a floor drain.
  4. Orient the discharge pipe so it cannot scald people.
  5. Do not install any isolation valve between the boiler and the relief valve.
  6. Check that the expansion tank piping is at least 3/4 in.

Applies to: Vitorond 100 VR1 40 to 63, 161 to 245

More boiler guides

Take it to the job

All guides, error codes and tips work offline in the HVACopedia app.

Open the app

Source: Vitorond 100 VR1 installation and service instructions, p. 20. Written in our own words; check the manual for your exact model.

For licensed technicians. Gas, electrical and refrigerant work must be done by a qualified, licensed person. Shut off power and gas before servicing, never bypass a safety control, and follow the manufacturer’s manual for the exact model; it and local codes always take priority. HVACopedia is not affiliated with any manufacturer; brand and model names only identify the equipment.