What is going on
Connections are made in the field and need approved pipe sealant or teflon tape. The boiler has heating supply and return, gas (1 in. NPTF), condensate drain, drain and fill points, PRV, and DHW supply and return. Power supply is covered in the electrical section.
Check in this order
- Use approved pipe sealant or teflon tape on all installation fittings.
- Make the heating supply and return connections to the boiler.
- Connect the gas supply to the 1 in. NPTF gas connection.
- Route the condensate drain to the boiler outlet.
- Connect the electrical supply as described in the electrical connections section.
Applies to: Vitodens 200-W B2HA 45, 60 piping
More boiler guides
Take it to the job
All guides, error codes and tips work offline in the HVACopedia app.
Source: Vitodens 200-W B2HA 45, 60 Installation Instructions, p. 11-12. Written in our own words; check the manual for your exact model.
For licensed technicians. Gas, electrical and refrigerant work must be done by a qualified, licensed person. Shut off power and gas before servicing, never bypass a safety control, and follow the manufacturer’s manual for the exact model; it and local codes always take priority. HVACopedia is not affiliated with any manufacturer; brand and model names only identify the equipment.