Pre-start checks before first firing
What is going on
Checks to complete before the burner is started.
Check in this order
- Confirm the water quality was tested and meets the system-fill guidelines.
- Open the combustion chamber door and confirm all turbulators are fully inserted into the flue passages.
- Confirm combustion air and ventilation openings in the mechanical room are open.
- Confirm the heating system is filled and fully purged of air.
- Check the cold fill pressure of the heating system.
- Check the oil supply or natural or propane gas supply pressure.
- Confirm a barometric draft regulator is installed (field supplied).
- Confirm the cleanout openings near the flue gas collar are tightly closed.
Applies to: Vitorond 200 VD2A boilers
More boiler guides
Take it to the job
All guides, error codes and tips work offline in the HVACopedia app.
Source: Vitorond 200 VD2A installation manual, p. 35. Written in our own words; check the manual for your exact model.
For licensed technicians. Gas, electrical and refrigerant work must be done by a qualified, licensed person. Shut off power and gas before servicing, never bypass a safety control, and follow the manufacturer’s manual for the exact model; it and local codes always take priority. HVACopedia is not affiliated with any manufacturer; brand and model names only identify the equipment.