What is going on
Continuation of the LON layouts with on-site cable and LON plugs or junction boxes.
Check in this order
- For runs up to 3000 ft (900 m), use LON plugs with on-site cable, up to 30 participants.
- For runs up to 3000 ft (900 m) with junction boxes, use LON cable 23 ft (7 m) to the sockets and on-site cable between sockets.
- Place the terminal end resistor at the far end of the line.
Applies to: Vitotronic 300 GW6B, LON network
More boiler guides
Take it to the job
All guides, error codes and tips work offline in the HVACopedia app.
Source: Vitotronic 300 GW6B installation and service manual, p. 47. Written in our own words; check the manual for your exact model.
For licensed technicians. Gas, electrical and refrigerant work must be done by a qualified, licensed person. Shut off power and gas before servicing, never bypass a safety control, and follow the manufacturer’s manual for the exact model; it and local codes always take priority. HVACopedia is not affiliated with any manufacturer; brand and model names only identify the equipment.