What is going on
The DHW relief valve protects the domestic hot water side from pressure built up during DHW heating. The system must be leak tested first, per the boiler installation instructions.
Check in this order
- Leak test the system before installing the valve.
- Install the 3/4 in tee on the field-supplied piping from the CombiPLUS A.
- Install the 150 psi PRV on the tee, mounted vertically in the DHW supply as close to the CombiPLUS heat exchanger as possible.
- Do not put a shutoff valve between the PRV and the heat exchanger or in the drain pipe.
- Run the drain pipe, same diameter as the valve outlet, to a safe disposal point with a downward slope from the valve.
- Apply the scald danger label to the boiler as shown.
- Follow local code. If local code requires a different relief valve, use that valve instead of the one supplied.
Applies to: Vitodens 100-W WB1B with CombiPLUS
More boiler guides
Take it to the job
All guides, error codes and tips work offline in the HVACopedia app.
Source: Vitodens 100-W, WB1B CombiPlus Installation & Service Instructions, p. 34. Written in our own words; check the manual for your exact model.
For licensed technicians. Gas, electrical and refrigerant work must be done by a qualified, licensed person. Shut off power and gas before servicing, never bypass a safety control, and follow the manufacturer’s manual for the exact model; it and local codes always take priority. HVACopedia is not affiliated with any manufacturer; brand and model names only identify the equipment.