What is going on
Fit the factory pressure relief valve and air vent, then run the discharge pipe to a floor drain. The discharge must never go outdoors.
Check in this order
- Apply pipe sealant to both ends of fittings B, D, F and G, then fit them into coupling A and tees C.
- Install the pressure relief valve H and the air vent E and tighten both.
- Run the relief discharge pipe with an unthreaded end, and end it about 6 in. (150 mm) above the floor drain.
- Do not fit any shutoff valve in the discharge pipe, do not reduce its diameter (minimum 3/4 in.), and do not fit an isolation valve between the boiler and the relief valve.
- Position the discharge so it cannot scald anyone nearby.
Applies to: Vitocrossal 300 CU3A 26 to 199
More boiler guides
Take it to the job
All guides, error codes and tips work offline in the HVACopedia app.
Source: Vitocrossal 300 CU3A 26 to 199 installation instructions, p. 16. Written in our own words; check the manual for your exact model.
For licensed technicians. Gas, electrical and refrigerant work must be done by a qualified, licensed person. Shut off power and gas before servicing, never bypass a safety control, and follow the manufacturer’s manual for the exact model; it and local codes always take priority. HVACopedia is not affiliated with any manufacturer; brand and model names only identify the equipment.