Hydrostatic pressure test of the pressure vessel
What is going on
Mandatory test after assembly and before any other piping, controls or safety devices are connected to the pressure vessel. Install the sensor well and a temporary air vent first.
Check in this order
- Install the supplied R e in. plug in the tapping on top of the rear section for the test.
- Install the stainless steel sensor well in the c in. opening with hemp and pipe dope.
- Close the main supply and return with blank metal plates and the supplied metric flanges. Fit a pressure gauge (0-150 psig) to the safety header and another automatic air vent to bleed air.
- Fill with room temperature water and make sure all air is vented.
- Test at a minimum of 110 psig. The maximum is 1.5 times the maximum operating pressure of the boiler and must not exceed 120 psig. If city pressure is too low, use a hand pump on the boiler drain valve.
- Hold the test pressure for 30 minutes. Check top push nipple ports with a flashlight and bottom push nipple ports by sliding cardboard under the cast iron block.
- After the test, release pressure slowly, remove the temporary air vent, and close the opening with the supplied plug and hemp and pipe dope.
- Remove the metal plates and flanges used for the test after it passes.
Applies to: Vitorond 200 VD2 320 to 1080
More boiler guides
Take it to the job
All guides, error codes and tips work offline in the HVACopedia app.
Source: Vitorond 200, VD2 Series 320 to 1080 Installation Instructions, p. 18. Written in our own words; check the manual for your exact model.
For licensed technicians. Gas, electrical and refrigerant work must be done by a qualified, licensed person. Shut off power and gas before servicing, never bypass a safety control, and follow the manufacturer’s manual for the exact model; it and local codes always take priority. HVACopedia is not affiliated with any manufacturer; brand and model names only identify the equipment.