Piping rules for the boiler water connections.

Check in this order

  1. Locate the safety header on the main supply header.
  2. Install the supplied air vent and pressure relief valve on the supply header. An alternate PRV location is the boiler supply line.
  3. Connect the precharged expansion tank and any automatic feed water to the boiler return.
  4. Install the boiler pump on the return pipe so it pumps water into the boiler.
  5. Install the supplied low water cut-off directly on the safety header or in the piping above the pressure vessel.
  6. Close off all unused connections that are not used for water or controls.
  7. Make all connections free of load and torque stress.
  8. Do not connect the heating system to the safety header.
  9. Do not install a 4-way mixing valve; the boiler is for hot water heating only.
  10. Connect the system per the piping diagram on page 45 of the manual.

Applies to: CA3B Dual Fuel 2.5 to 6.0

More boiler guides

Take it to the job

All guides, error codes and tips work offline in the HVACopedia app.

Open the app

Source: Vitocrossal 300 CA3B Dual Fuel Series 2.5 to 6.0 installation instructions, p. 15. Written in our own words; check the manual for your exact model.

For licensed technicians. Gas, electrical and refrigerant work must be done by a qualified, licensed person. Shut off power and gas before servicing, never bypass a safety control, and follow the manufacturer’s manual for the exact model; it and local codes always take priority. HVACopedia is not affiliated with any manufacturer; brand and model names only identify the equipment.