A boiler stand is used for free-standing installation of one boiler. The stand must be anchored to the floor, and the wall location for the frame, bracket and vents is field-calculated because there is no mounting template.

Check in this order

  1. Anchor the stand securely to the floor using concrete expansion anchors (anchor size not legible in this copy).
  2. Attach the wall mounting bracket to the mounting frame with the supplied hardware.
  3. Confirm the bracket is level.
  4. Move the rack into position and secure it to the floor, and to the wall if needed.

Applies to: Vitodens 200-W B2HA 45, 60 frame mounting

More boiler guides

Take it to the job

All guides, error codes and tips work offline in the HVACopedia app.

Open the app

Source: Vitodens 200-W B2HA 45, 60 Installation Instructions, p. 16. Written in our own words; check the manual for your exact model.

For licensed technicians. Gas, electrical and refrigerant work must be done by a qualified, licensed person. Shut off power and gas before servicing, never bypass a safety control, and follow the manufacturer’s manual for the exact model; it and local codes always take priority. HVACopedia is not affiliated with any manufacturer; brand and model names only identify the equipment.