What is going on
Set the expansion vessel precharge first, then fill and vent the system at the correct pressure.
Check in this order
- With the system cold, check the expansion vessel precharge. If it is lower than the static system pressure, top it up with nitrogen until it is 1.5 to 3 psi (0.1 to 0.2 bar) above static pressure.
- Close the gas shutoff valve.
- Open any installed shutoff valves.
- Fill the heating system with water and vent it, until the fill pressure is 1.5 to 3 psi (0.1 to 0.2 bar) above the vessel precharge, using the boiler drain/fill valve.
- Mark the set pressure on the temperature and pressure gauge.
- Record the fill volume, water hardness and pH value.
- Return the shutoff valves to their operating position.
- Close the boiler drain/fill valve.
Applies to: Vitocrossal 300 CU3A 26 to 199
More boiler guides
Take it to the job
All guides, error codes and tips work offline in the HVACopedia app.
Source: Vitocrossal 300 CU3A 26 to 199 installation instructions, p. 20. Written in our own words; check the manual for your exact model.
For licensed technicians. Gas, electrical and refrigerant work must be done by a qualified, licensed person. Shut off power and gas before servicing, never bypass a safety control, and follow the manufacturer’s manual for the exact model; it and local codes always take priority. HVACopedia is not affiliated with any manufacturer; brand and model names only identify the equipment.