Connect the vent to the boiler
What is going on
Venting must be short and straight with a supported horizontal run. Use the factory vent adaptor on the flue gas collar.
Check in this order
- Route the vent the shortest way with the fewest elbows. Rearrange water piping if needed for a closer chimney connection.
- Support horizontal runs so they do not sag, and avoid long horizontal runs.
- Give horizontal runs at least 1/4 in rise per ft from the boiler to the vent terminal.
- Strap horizontal runs every 4 ft (1.2 m) with metal strapping.
- Attach the factory vent pipe adaptor to the flue gas collar with three equally spaced corrosion resistant self-tapping screws and high temperature silicone, or equivalent.
- Connect the chimney through a field supplied 18 in (457 mm) long, slightly inclined intermediate section of 5 in outside diameter flue pipe.
- Drill a 1/2 in opening on the side of the vent pipe, about three times the vent pipe diameter from the flue collar, for flue gas analysis.
- Seal all flue pipe joints.
- Insulate any uninsulated vent pipe to reduce flue gas cooling and noise.
- Install an outside rain cap and use a field supplied M-barometric damper for oil, per the draft control maker's instructions.
- In Canada, fit the blocked vent safety switch. For direct vent, follow the separate direct vent instructions.
Applies to: VR1 22 to 33, 91 to 140
More boiler guides
Take it to the job
All guides, error codes and tips work offline in the HVACopedia app.
Source: Vitorond 100 installation and service manual, p. 15. Written in our own words; check the manual for your exact model.
For licensed technicians. Gas, electrical and refrigerant work must be done by a qualified, licensed person. Shut off power and gas before servicing, never bypass a safety control, and follow the manufacturer’s manual for the exact model; it and local codes always take priority. HVACopedia is not affiliated with any manufacturer; brand and model names only identify the equipment.