Connect gateway to Vitotronic control on 120 VAC
What is going on
Connection for GW6B and MW2C controls when the gateway is powered from 120 VAC. The lead and cascade control need the LON card.
Check in this order
- Install the LON communication card in the lead or cascade Vitotronic 300 GW6B. The lag controls also need LON communication.
- Plug the supplied CAT-5 cable into the control and into the gateway RJ45 socket.
- Plug the BACnet/IP RJ45 cable into the gateway.
- Plug the 120 VAC power cord into the gateway.
Applies to: Vitotronic 300 GW6B, Vitotronic 300-K MW2C
More boiler guides
Take it to the job
All guides, error codes and tips work offline in the HVACopedia app.
Source: Versatronik 585 and 585D BACnet IP gateway manual, p. 9. Written in our own words; check the manual for your exact model.
For licensed technicians. Gas, electrical and refrigerant work must be done by a qualified, licensed person. Shut off power and gas before servicing, never bypass a safety control, and follow the manufacturer’s manual for the exact model; it and local codes always take priority. HVACopedia is not affiliated with any manufacturer; brand and model names only identify the equipment.