Viessmann · Boiler troubleshooting
Condensate drain installation and neutralization
What is going on
Condensate from the boiler and flue pipe is acidic (pH 3 to 4). It must go to the drain through a trap, and a neutralizer is used where local code requires it.
Check in this order
- Run the condensate drain pipe with a continuous fall toward the drain.
- Use corrosion-resistant materials only, such as braided hose. Do not use galvanized pipe or copper-containing fittings.
- Install a trap in the drain to stop flue gas leakage, and make the outlet visible with a stench trap.
- If the boiler condensate outlet is below the drain, install a condensate pump.
- If a neutralizer is used, vent the pipe between the siphon trap and the neutralizer.
- Check the neutralizer granulate level several times in the first year to set the refill interval. Treated water should be above pH 6.5 when discharged.
- Confirm local waterworks and waste water rules before installing the neutralizer.
Applies to: B2HB 19 to 57, 68 to 199
More boiler guides
Take it to the job
All guides, error codes and tips work offline in the HVACopedia app.
Source: Viessmann Vitodens 200-W B2HB technical data manual, p. 20. Written in our own words; check the manual for your exact model.
For licensed technicians. Gas, electrical and refrigerant work must be done by a qualified, licensed person. Shut off power and gas before servicing, never bypass a safety control, and follow the manufacturer’s manual for the exact model; it and local codes always take priority. HVACopedia is not affiliated with any manufacturer; brand and model names only identify the equipment.