Viessmann · Boiler troubleshooting

Combustion air duct requirements

Vitorond 100 VR1

What is going on

Outdoor air ducts must meet these size rules. Sizing for openings is in the combustion air opening table.

Check in this order

  1. Make the duct cross-sectional area along its full length at least equal to the free area of the openings it connects.
  2. Keep the minimum duct dimension at 3 in (76 mm) at any section.
  3. Keep the outside air intake at least 1 ft (0.3 m) above the expected snow level.
  4. If a damper is in a combustion air opening, interlock it so no burner can start until the damper is fully open.

Applies to: VR1 22 to 33, 91 to 140

More boiler guides

Take it to the job

All guides, error codes and tips work offline in the HVACopedia app.

Open the app

Source: Vitorond 100 installation and service manual, p. 9. Written in our own words; check the manual for your exact model.

For licensed technicians. Gas, electrical and refrigerant work must be done by a qualified, licensed person. Shut off power and gas before servicing, never bypass a safety control, and follow the manufacturer’s manual for the exact model; it and local codes always take priority. HVACopedia is not affiliated with any manufacturer; brand and model names only identify the equipment.