Confirm the flue and combustion air path is sound before the boiler is started.
Check in this order
- Confirm the flue gas route is unrestricted.
- Confirm the positive pressure flue system is gas-tight.
- Check that the inspection port covers are secure and tight.
- Confirm the combustion air openings are open and cannot be closed.
- Confirm the flue installation follows current codes for flue systems.
- Do not commission if the flue is leaking or blocked, or combustion air is short. Poisoning from carbon monoxide can result.
- Keep combustion air vents non-closable and stop condensate drainage into them with a wind protector.
Applies to: Vitodens 100-W B1HE/B1KE
More boiler guides
Take it to the job
All guides, error codes and tips work offline in the HVACopedia app.
Source: Vitodens 100-W B1HE/B1KE installation manual, p. 24. Written in our own words; check the manual for your exact model.
For licensed technicians. Gas, electrical and refrigerant work must be done by a qualified, licensed person. Shut off power and gas before servicing, never bypass a safety control, and follow the manufacturer’s manual for the exact model; it and local codes always take priority. HVACopedia is not affiliated with any manufacturer; brand and model names only identify the equipment.