What is going on

Confirm the vent termination meets height and spacing limits from the manual.

Check in this order

  1. Measure the vent termination height above grade and the anticipated snow level.
  2. Confirm it is at least 12 in above snow level.
  3. On sloped or flat roofs, confirm the vent height and obstruction clearances.
  4. Confirm the total equivalent length (exhaust plus intake) does not exceed 198 ft (60 m).
  5. Add elbow equivalent lengths to the total before checking the limit.

Applies to: Vitocrossal 200 CI2 direct and single-pipe venting

More boiler guides

Take it to the job

All guides, error codes and tips work offline in the HVACopedia app.

Open the app

Source: Vitocrossal 200 CI2 Installation manual, p. 56, 58, 59. Written in our own words; check the manual for your exact model.

For licensed technicians. Gas, electrical and refrigerant work must be done by a qualified, licensed person. Shut off power and gas before servicing, never bypass a safety control, and follow the manufacturer’s manual for the exact model; it and local codes always take priority. HVACopedia is not affiliated with any manufacturer; brand and model names only identify the equipment.