Boiler pressure test before connecting piping and power

Vitorond 200 VD2A

What is going on

Leak and hydrostatic test on the installed boiler with supply and return headers in place. The boiler must pass before it is connected to piping or power.

Check in this order

  1. Install supply and return headers with gauge, thermometer, air vent, low water cut-off, drain valve and bypass pump. Pipe to the isolation valves and close them.
  2. Install temporary caps on the relief valve and expansion tank nipples.
  3. Connect a hose to the boiler drain valve and fill slowly until the gauge reads the maximum test pressure.
  4. Hold pressure for 30 minutes. Do not leave the boiler unattended.
  5. Inspect all push nipples and pipe joints with a flashlight. Place paper under the block to catch drips from bottom nipples.
  6. After 30 minutes, open the drain valve slowly to release pressure, remove the caps and install the relief valve and expansion tank right away.

Applies to: Installed boiler before start-up

More boiler guides

Take it to the job

All guides, error codes and tips work offline in the HVACopedia app.

Open the app

Source: Vitorond 200, VD2A Series Installation, p. 24. Written in our own words; check the manual for your exact model.

For licensed technicians. Gas, electrical and refrigerant work must be done by a qualified, licensed person. Shut off power and gas before servicing, never bypass a safety control, and follow the manufacturer’s manual for the exact model; it and local codes always take priority. HVACopedia is not affiliated with any manufacturer; brand and model names only identify the equipment.