The boiler must be leak tested and hydrostatically pressure tested before connection to piping or power. Test pressure is between 110 and 120 psig (689 to 827 kPa).
Check in this order
- Install supply and return headers with pressure gauge, temperature gauge, air vent, low water cut-off, drain valve and bypass pump. Pipe up to isolation valves and close them.
- Install temporary caps on the relief valve and expansion tank nipples.
- Connect a hose to the boiler drain valve and fill slowly until the gauge reads a maximum of 120 psig (827 kPa).
- Hold pressure for 30 minutes and do not leave the boiler unattended.
- Check all push nipples and pipe connections for leaks with a flashlight. Place paper under the cast iron block to catch minor leaks.
- After 30 minutes, open the drain valve slowly to release pressure.
- Remove caps and install the relief valve and expansion tank right away.
Applies to: Vitorond 200 VD2 boiler before startup
More boiler guides
Take it to the job
All guides, error codes and tips work offline in the HVACopedia app.
Source: Vitorond 200 VD2 installation manual, p. 26. Written in our own words; check the manual for your exact model.
For licensed technicians. Gas, electrical and refrigerant work must be done by a qualified, licensed person. Shut off power and gas before servicing, never bypass a safety control, and follow the manufacturer’s manual for the exact model; it and local codes always take priority. HVACopedia is not affiliated with any manufacturer; brand and model names only identify the equipment.