Apply strain relief to external cables
What is going on
Use the strain relief method that matches the cable type.
Check in this order
- For on-site cables cut the tip from the rubber cable restraint, feed the cable through it, then seat the restraint in the connection housing.
- Strip up to 4 in. (100 mm) of insulation from on-site cables.
- For cables with a moulded strain relief remove the rubber strain relief from the housing and discard it.
- Plug the cable into the matching counter plug on the control board.
- Fit the cable's own strain relief into the empty mount of the connection housing.
Applies to: Vitocrossal 300 CU3A 26 to 199
More boiler guides
Take it to the job
All guides, error codes and tips work offline in the HVACopedia app.
Source: Vitocrossal 300 CU3A installation manual, p. 25. Written in our own words; check the manual for your exact model.
For licensed technicians. Gas, electrical and refrigerant work must be done by a qualified, licensed person. Shut off power and gas before servicing, never bypass a safety control, and follow the manufacturer’s manual for the exact model; it and local codes always take priority. HVACopedia is not affiliated with any manufacturer; brand and model names only identify the equipment.