Viessmann · Boiler troubleshooting

Application 4: wiring and piping notes for air handler and radiant loop

Vitocrossal 300 CU3A

What is going on

Application CU3I 2ZC2ZP.01. The CU3A is a high-mass boiler, so primary/secondary piping is not required. A thermostatic mixing valve protects the radiant floor from excessive hot water. Heat demand from the air handler must be a dry (potential-free) contact.

Check in this order

  1. Wire the air handler heat demand as a dry, potential-free contact.
  2. Wire the radiant circuit call as a dry contact from a thermostat, zone valve or multi-zone controller.
  3. Install the jumper between the 40A plug and the 157 plug.
  4. If P4 is controlled by the air handler, do not wire a pump.
  5. Use the pressure drop and pump sizing chart for the CU3A 94/125 or 160/199 model as applicable.

Applies to: Application 4 (CU3I 2ZC2ZP.01)

More boiler guides

Take it to the job

All guides, error codes and tips work offline in the HVACopedia app.

Open the app

Source: Vitocrossal 300 CU3A Application Guide, p. 30-31. Written in our own words; check the manual for your exact model.

For licensed technicians. Gas, electrical and refrigerant work must be done by a qualified, licensed person. Shut off power and gas before servicing, never bypass a safety control, and follow the manufacturer’s manual for the exact model; it and local codes always take priority. HVACopedia is not affiliated with any manufacturer; brand and model names only identify the equipment.